Maintenance - Ashburn, Atlanta, Singapore - Virtual Private Data Center
Scheduled Maintenance Report for phoenixnap
Completed
The scheduled maintenance has been completed.
Posted May 06, 2024 - 07:00 MST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted May 06, 2024 - 01:00 MST
Scheduled
Our engineering team will be performing a scheduled maintenance on Virtual Private Data Center (VPDC) in Ashburn, Atlanta and Singapore.

Site
ASH, ATL, SIN - VPDC

Product
Virtual Private Data Center

Reason
Patching to infrastructure components

Impacted components
VMware Cloud Director, VMware Cloud Director Availability, Veeam Backup & Replication, Veeam Backup Enterprise Manager, Veeam Cloud Connect & Replication, Veeam Service Provider Console, Zerto

Details / Risks
Management portals for the afore-mentioned products will be intermittently available while services are interrupted. Backups and replications might be interrupted but will be resumed upon maintenance completion.

Date & Time (MST)
May 6, 2024 01:00 AM to May 6, 2024 07:00 AM

Date & Time (CEST)
May 6, 2024 10:00 AM to May 6, 2024 4:00 PM

Duration
6 hours
Posted Apr 24, 2024 - 04:19 MST
This scheduled maintenance affected: Singapore (Virtual Private Data Center (VPDC)), Ashburn (Virtual Private Data Center (VPDC)), and Atlanta (Disaster Recovery as a Service (DRaaS) - Veeam Cloud Connect Replication).