Maintenance - Ashburn - Storage
Scheduled Maintenance Report for phoenixnap
Completed
The scheduled maintenance has been completed.
Posted Nov 19, 2024 - 05:00 MST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Nov 19, 2024 - 01:00 MST
Scheduled
Our engineering team will be performing a scheduled maintenance on Virtual Private Data Center / Data Secured Cloud in Ashburn.

Site
ASH - VPDC
ASH - DSC

Product
Storage

Reason
Product update / upgrade to version 6.1.2.500

Impacted components
All Flash Storage Array

Details / Risks
During the OS upgrade, services will failover to the other controller, which might cause a brief interruption to the data services. This is a normal process and we do not anticipate any issues during this maintenance. Backup jobs will be paused during the maintenance and will be resumed after the storage is upgraded.

Date & time (MST)
Nov 19, 2024 1:00 AM to Nov 19, 2024 05:00 AM

Date & time (CET)
Nov 19, 2024 09:00 AM to Nov 19, 2024 01:00 PM

Duration
4 hours