Maintenance - Ashburn - Backup as a Service (BaaS) Cloud Backup Standard / Advanced

Scheduled Maintenance Report for phoenixnap

Completed

The scheduled maintenance has been completed.
Posted Jun 25, 2025 - 13:01 MST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jun 25, 2025 - 09:01 MST

Scheduled

Our engineering team will be performing a scheduled maintenance on Backup as a Service in Ashburn.

Site
ASH - VPDC - BaaS

Product
Cloud Backup Standard / Advanced

Reason
Product update / upgrade to version 12.3.2.3617

Impacted components
Veeam Backup Enterprise Manager, Veeam Backup & Replication

Details / Risks
During this maintenance window, Veeam services will be stopped and backup jobs & replications might be interrupted.
Job management using the ashveeambackups.phoenixnap.com
will be unavailable.
All services will resume as soon as the maintenance is concluded.

Date & time (MST)
Jun 25, 2025 9:00 AM to Jun 25, 2025 01:00 PM

Date & time (CEST)
Jun 25, 2025 06:00 PM to Jun 25, 2025 10:00 PM

Duration
4 hours
Posted Jun 17, 2025 - 09:43 MST
This scheduled maintenance affected: Ashburn (Virtual Private Data Center (VPDC), Backup as a Service (BaaS) - Veeam Managed Backups, Backup as a Service (BaaS) - Veeam Cloud Connect).