Maintenance - Phoenix - VPDC
Scheduled Maintenance Report for phoenixnap
Completed
The scheduled maintenance has been completed.
Posted Apr 15, 2024 - 13:00 MST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Apr 15, 2024 - 09:00 MST
Scheduled
Valued Client,

Our engineering team will be performing a scheduled maintenance in PHX VPDC.

Sites
PHX - VPDC

Product
Zerto Virtual Replication

Reason
Upgrade to Zerto Version 10

Impacted components
Zerto Virtual Manager

Details / Risks
During the maintenance, there will be a temporary disruption to access to the
Zerto Virtual Manager.

Date & Time (MST): A
PHX VPDC: Apr 15, 2024 09:00 AM to Apr 15, 2024 01:00 PM

Date & Time (CET):
PHX VPDC: Apr 15, 2024 06:00 PM to Apr 15, 2024 10:00 PM

Duration
4 hours

Thank you for your understanding and patience as we continue to work toward
providing you with the best service possible. Our teams will take every
necessary precaution to mitigate any negative impact during the announced
maintenance.

If you have any questions regarding this maintenance, please contact one of our
NOC team members at 877.749.2656 or noc@phoenixnap.com.

Thank you,
phoenixNAP Cloud Services Team
Posted Apr 01, 2024 - 11:43 MST
This scheduled maintenance affected: Phoenix (Virtual Private Data Center (VPDC)).